Short answer: 14 days from signed proposal to your first sauna session for residential installs in Dubai. Commercial wellness room installs (hotel SPA, gym, multi-room) run 6–12 weeks.

Here’s exactly how those 14 days break down – and where the schedule actually slips when projects do go long.

The 14-day residential timeline

DayActivity
Day 0Site visit, design conversation, deposit (50%)
Day 1–3Final design + materials list + permits if required
Day 4–6Materials prep, frame and insulation delivery
Day 7–10Build: frame, insulation, vapor barrier, electrical, ventilation
Day 11–13Cladding, glass, heater install, controls, finishes
Day 14Commissioning: full thermal cycle test, electrical safety check, handover

That’s the plan. About 75% of our residential sauna installs in Dubai hit this 14-day window. The rest stretch by 1–4 days for the reasons below.

What stretches the schedule

1. Electrical capacity

If your villa’s electrical panel doesn’t have a free 16–32A breaker for a dedicated sauna circuit, we need a DEWA-licensed electrician to add one. That coordination adds 2–5 days. We flag this on the site visit so you know in advance.

2. Building permission / HOA

Apartment installs and townhouses sometimes need building manager approval. We’ve seen this take anywhere from 1 day (responsive HOA) to 14 days (slow building manager who wants engineering letters before approving). For penthouse and rooftop installs, this jumps to 2–6 weeks because of structural and Civil Defense sign-offs.

3. Material supply

Standard cedar, hemlock, thermowood, and Harvia/Tylö heaters we keep in stock. Custom orders – premium HUUM heaters, specific glass thicknesses, custom door hardware – can add 1–3 weeks while we import. We tell you the lead time at design stage.

4. Ventilation routing

Most Dubai installs route exhaust into existing bathroom or AC duct returns. When a building’s ductwork is unusually configured, we sometimes have to route through ceiling void or external wall – adds 2–4 days of carpentry and core drilling.

The commercial timeline (6–12 weeks)

For hotel SPAs, gym wellness zones, and multi-room recovery facilities, the timeline is fundamentally different because of permits, M&E coordination, and the sheer scope.

WeekActivity
Week 1Site survey, brief, conceptual design
Week 2–3Detailed design, BOQ, permit submissions (Civil Defense, DEWA, DM)
Week 4–6Permit approvals (parallel: material orders, fabrication)
Week 7–9Build: structural, M&E, HVAC, plumbing, electrical
Week 10–11Finishes, equipment install, commissioning
Week 12Staff training, handover, opening

The longest pole on commercial is almost always permits, not construction. We submit early and follow up weekly. We don’t sub out permit work – our design lead handles it directly.

Can it be done faster?

Sometimes, in narrow circumstances:

What never works: skipping the site visit. Every “rush quote” we get asked to give without seeing the space turns into a renegotiation later. The 90-minute site visit is the highest-leverage hour of the project.

What you do during the 14 days

Almost nothing, honestly. Once we start the build:

How to start

The first step is a 90-minute site visit – free for Dubai addresses. WhatsApp us with photos of the intended space, your address, and a rough budget range. We book the visit and arrive on time. After the visit you get the design and quote within 5 days. After signing, day 1 of the 14-day window starts.